BQE Panel: Decades of Construction Coming

DOT project lead Tiffany-Ann Taylor (left) and other meeting attendees.

Is a long-awaited plan to repair the highway’s triple cantilever on a “collision course” with an equally ambitious project in Red Hook?

BY JACK DELANEY | jack@queensledger.com 

BROOKLYN HEIGHTS — If you live near Brooklyn Bridge Park, you may have already resigned yourself to the relentless din of jackhammers and rattling trucks.

But on October 6, the first public info session for the city’s recently-announced plan to repair the BQE shed more light on the potentially decades of construction that may be facing Brooklyn Heights, DUMBO, Cobble Hill, and parts of Red Hook — a nexus of neighborhoods that looks set to host at least four major development projects in the near future.

The NYC Department of Transportation (DOT) aims to start construction on BQE Central, which stretches from Atlantic Avenue and under the Promenade to Sands Street, in 2029 and complete all work by 2040.

To the north, a separate developer is seeking to add stories to two of the old Watchtower buildings at 25 and 30 Columbia Heights — once the global headquarters of Jehovah’s Witnesses — and convert the entire campus into more than 600 units of housing.

To the south, a similar proposal would repurpose the former Long Island College Hospital (known to longtime residents as LICH) to create another high-density apartment complex.

Most significantly, the $4 billion repairs to BQE Central would almost certainly coincide with the $3.5 billion redevelopment of the Brooklyn Marine Terminal (BMT) in northern Red Hook, where the city hopes to replace part of the dilapidated dockyards with roughly 4,000 homes, wrapping up by 2039.

The city’s current proposal involves a bypass that would extend over the Brooklyn Bridge.

There is substantial overlap between the two projects: Tiffany-Ann Taylor, who moderated last week’s info session, leads the DOT team responsible for working on the BQE and also represents the agency in ongoing negotiations over the BMT. “We are in very close coordination,” she noted.

Yet residents of the Columbia Street Waterfront District, which is immediately adjacent to the port, have raised concerns that the latest version of the BMT proposal — presented a day after the BQE forum — did not explicitly mention its sister project.

“The two meetings last week make it crystal clear,” wrote Randy Gordon, president of the Columbia Street Waterfront Association. “The Brooklyn Marine Terminal redevelopment and the BQE Central projects are on a collision course, with our neighborhood caught between.”

“Tear It Down?”

BQE Central, which spans 1.5 miles and includes a stacked structure called the triple cantilever, was built by the infamous planner Robert Moses during the 1940s. It was intended to last for approximately 50 years, however, and in the 2010s engineers began sounding the alarm that the triple cantilever was rapidly degrading.

The Mamdani administration’s new plan would extend BQE Central’s lease on life by an estimated 40 years through targeted repairs, but leaves its basic parameters untouched — the highway will remain two lanes, and no interchanges will be altered.

The proposal relies on two temporary bypass structures, one over Furman Street and the other leapfrogging over the Brooklyn Bridge, which will absorb traffic while work is completed. Taylor stressed that the DOT will maintain access to at least some portion of the Promenade at all times during construction.

Some residents who tuned into the virtual info session wondered why the elaborate bypasses were necessary. “Can you help us understand,” said Barry Harbaugh of Brooklyn Heights, “why this very expensive, not that long-term, and extremely intense project is preferable to just shutting down this part of the BQE and doing the job for real?”

Other attendees seized on the news that the city would need to pass a parkland alienation bill at the state level in order to move forward, the same measure needed to create the planned casino in the parking lot next to Citi Field in Queens, because the project will annex a corner of Squibb Park.

Andrew McLaughlin, a local who called the BQE a “horrible act of violence” that divided neighborhood life, saw the state protocol as a golden opportunity: “Alienation of parkland gives us a powerful lever to kill this entire plan through the legislature,” he said, “by denying permission to seize our neighborhoods’ land for these temporary highways.”

But Taylor and her team defended both their plan and the BQE as a whole, affirming that it still serves as a major transportation corridor — and that this proposal, while flawed, is the best possible intervention given the constraints.

“We cannot touch the actual ramps to the BQE at this time, because that would trigger federal review and require their involvement,” Taylor explained. “It’s probably very clear to all of you that the relationship as it relates to transportation in New York is delicate. That’s why we’ve decided to at least offer this conservative proposal to rehabilitate BQE Central, to ensure that it’s safe to navigate.”

“Trust me, nobody wants to spend nearly $4 billion,” she concluded. “But here we are.”

The DOT will be holding public meetings on November 10 and 12 as it prepares to enter the environmental review process, and will be accepting formal comments until November 23. For more info, visit nyc.gov/html/dot/html/infrastructure/bqecentral.shtml.